Case Study

Naber Business Park Grading – Material Processing & Haul Off (St. Michael, MN)

Project Overview

Our team was contracted by the City of St. Michael, MN, to complete large-scale grading and material processing at the future Naber Business Park.

The 30-acre industrial site required:

  • Full topsoil stripping and precise grading for future street and building pad elevations
  • Processing of more than 500,000 tons of excess soils
  • Export of all excess materials off-site within an 18-month deadline, avoiding $1,500/day in potential liquidated damages

During the process, we converted the excavated material into high-quality aggregate products:

  • 360,000 tons of screened sand
  • 90,000 tons of Class 5 gravel
  • 50,000 tons of screened 1 ½” rock, hauled to Fehn Aggregates for future washing and distribution

Challenges & Solutions

1. Large-Scale Material Processing

Challenge: Processing a half-million tons of variable native material, including silty soils that periodically impacted production quality.

Solution: Plant operators actively monitored consistency and adjusted crushing/screening operations in real time to ensure all products met MnDOT specifications.

2. Logistics & Haul-Off Efficiency

Challenge: Meeting the aggressive haul-off schedule required continuous trucking operations.

Solution: At peak performance, up to 50 trucks per day were dispatched. Our dispatch and trucking teams coordinated closely to reduce wait times and maintain a continuous outbound flow.

3. Sales & Market Demand

Challenge: Identifying buyers for large volumes of processed materials was essential to avoid costly stockpiling delays.

Solution: We expanded sales and marketing outreach, securing regional buyers and construction projects to absorb the sand, gravel, and rock.

Project Impact

Through proactive planning, adaptive processing techniques, and strong coordination between our processing, logistics, and sales teams, we:

  • Completed the project within the 18-month timeframe
  • Avoided costly penalties
  • Delivered high-quality aggregate products into the local market, reinforcing our reputation for reliability and precision

At Fehn Companies, we don’t just move dirt — we transform challenges into opportunities, turning large-scale earthwork into lasting value for our clients and communities.

Explore more case studies

Rum River Campus Demolition – Anoka, MN

Rum River Campus Demolition – Anoka, MN

At Fehn Companies, we take pride in tackling complex demolition projects that require precision, planning, and experience. One project that stands out is the Rum River Campus Demolition at the historic Anoka State Hospital in Anoka, MN.

Read More »

50 Years of EarthWork Excellence

Contact Us Today

Start your project with Fehn Companies. Our team is equipped to handle all your earthwork and gravel mining needs.